Frost and snow couldn’t stop the construction of the trellises for the CellMon projects.
Thanks to the help of 3 helicopters, in the last two months Lepida has completed the construction works of numerous trellises: Neviano degli Arduini, Coli, Lesignano de’ Bagni, Bedonia, Lizzano in Belvedere, Carpineti, Casola Valsenio, Cerignale and Predappio.
Thanks to this final rush, the total amount of established trellises has reached 36 units, of which 28 are on-air with operating services that had daily piques of 1.4 Gbps.
This project, during the first three steps, has activated 24 systems, 2 more will be activated by February and 1 is under analysis.
Speaking of the 4th phase, services have already been activated on 4 systems, 8 are in the process of completion and 1 is in the process of issuing permits. 3 more systems are being submitted for permits and the right field has been searched for 2 more.
On phase V, 2 systems are being built, 6 are being presented and 5 are on the field.
Given the success of the initiative and that several Bodies still highlight the continuing presence of technological gaps in different areas of their territory, it is already being considered to start a further survey of uncovered areas by the end of the year.